Plymouth Twp. Road Work Updates for Nov. 26 to Dec. 1

Updates on the I-476 Mainline Construction Project.

The Pennsylvania Turnpike Commission will be hosting a construction update open house on Thursday, Nov. 29 from 5:30 to 7:30 p.m. at the Plymouth Township building.

General Construction Impacts:
Walsh Construction and their sub-contractors will be working around the clock throughout the week at various locations and neighborhoods adjacent to the six-mile construction area will experience general construction noise. Noise may include heavy equipment, lights (at night), vehicle-mounted safety lights (at all times), and backup alarms. All efforts are being taken to limit the impacts to the adjacent communities; however, night work is going to occur as needed and the PTC will not limit the contractor’s hours of operation.

Plymouth Township Roadwork:
Road work will take place on the following roadways between 7 a.m. and 6:30 p.m., Monday through Friday: Walton Rd., Apollo Rd., Township Line Rd.

Find out what's happening in Plymouth-Whitemarshwith free, real-time updates from Patch.

Road work will take place on the following roadways around the clock from Monday through Friday: Jocelyn Rd., Hickory Rd.

Structure work: Daytime: Hickory Rd. mainline bridge, Township Line Rd. mainline bridge.

Find out what's happening in Plymouth-Whitemarshwith free, real-time updates from Patch.

Retaining walls:

  • 24-hour: Jocelyn Rd., Hickory Rd., Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., Beacon Hill Cir., Jolly Rd.